Search

Search for a product, category, or catalog by name or description

Load Test Table

Load test table in accordance with Directive 2006/42/EC of the European Parliament of May 17, 2006

Conformity to Directive 2006/42/EC

In accordance with Directive 2006/42/EC of the European Parliament of 17 May 2006, it is imperative to inspect all lifting equipment mentioned below, according to the indicated methods.

Powered and manual forkl forklifts

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Frontal forklifts
Load test before first use and return to service.

Static test +25% of the SWL
Duration 1 hour

Dynamic test + 10% of the SWL
Undetermined duration
Trial under load every 6 months **Dynamic test + 10% of SWL** Undefined duration
In dynamic testing, it involves moving the loads to all possible positions specified by the manufacturer. During the static test, it involves lifting the masses for 1 hour and checking for any descent. The fork descent must not exceed **100mm during 10 min** and the tilt must be less than 5° during 10 min. After the one-hour static test, it is necessary to verify that there is no irreversible deformation.
Forklifts with an elevating operator's station
Reach trucks
Industrial towing tractors
platform trolley
Ride-on pallet trucks
Ride-on and pedestrian stackers
Manual lifting device
Load test before first use and commissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
No defined duration
Load test every 12 months **Dynamic test + 10% of the SWL** No defined duration
If placed on the market before October 1, 1989, the static test must be carried out with a load test + 33% of the SWL. Duration of the static test: 1 hour. The dynamic test, on the other hand, is performed with SWL + 10%.
If placed on the market between October 1, 1989, and December 31, 1995, the static test must be carried out with a test load + 33% of the SWL (Safe Working Load). The duration of the static test in this case is 15 minutes. The dynamic test is performed with the effective SWL at maximum height.
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Mobile Elevating Work Platform (MEWP)

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Vertical lift platform
Load test before first use and return to service.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10% of SWL
No defined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
In dynamic testing, it consists of moving the loads into all possible positions specified by the manufacturer. During the static test, it consists of lifting the masses for 1 hour and checking for any descent. The platform's descent must not exceed **100mm during 10 min**. After the one-hour static test, it is necessary to check that there is no irreversible deformation.
Multi-directional lifting platform
Truck with an elevating platform
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Auxiliary crane and lifting arm

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Auxiliary crane
Load test before first use and return to service.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10% of SWL
No defined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
In dynamic testing, it involves moving the loads to all possible positions specified by the manufacturer. During the static test, it involves lifting the masses for 1 hour and checking if there is any descent. The descent must not exceed **100mm during 10 min**. After the one-hour static test, it is necessary to check that there is no irreversible deformation.
Forest crane
Truck dump lifting arm
If commissioning is prior to 1993, the static test is performed with a load equivalent to the SWL + 50%.
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

TAIL LIFT

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Tail lift and wheelchair accessible
Load test before first use and recommissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
In dynamic testing, it consists of moving the loads into all possible positions specified by the manufacturer. During static testing, it consists of lifting the masses for 1 hour and checking for any descent. The tailgate's descent must not exceed 100mm over 10 min. After the one-hour static test, it is necessary to verify that there is no irreversible deformation.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Construction and public works machinery

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Telescopic handler
Load test before first use and return to service.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10% of SWL
No defined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
In dynamic testing, it consists of bringing the loads into all possible positions specified by the manufacturer. During the static test, it consists of lifting the masses for 1 hour and checking if there is any descent. The descent must not exceed 100mm during 10 min. After the one-hour static test, it is necessary to check that there is no irreversible deformation.
Dump truck
Bulldozer
Loader
Road-rail vehicle
Shovel and excavator
Dumper
Grader
Compactor
The semi-annual inspection only applies to devices equipped for lifting (if your machine has hydraulic safety valves, your machine is necessarily equipped for lifting). Otherwise, VGP inspections are only carried out annually.
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

MOBILE AND TOWER CRANE

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Lattice boom mobile crane
Load test before first use and return to service.

Static test +25% of the SWL
Duration 1 hour

Dynamic test + 10% of the SWL
Undetermined duration
Trial under load every 6 months **Dynamic test + 10% of SWL** Undefined duration
In dynamic testing, it involves bringing the loads to all possible positions specified by the manufacturer. During the static test, it involves lifting the masses for 1 hour and checking for any descent. The descent of the load must not exceed **100mm during 10 min**. After the one-hour static test, it is necessary to check that there is no irreversible deformation.
Telescopic boom mobile crane
Tower crane (component assembly)
Tower crane (automated)
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

OVERHEAD CRANES - JIB CRANE - HOIST

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Gantry crane, overhead crane
Load test before first use and recommissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 12 months **Dynamic test + 10% of the SWL** No defined duration
In dynamic testing, it involves bringing the loads to all possible positions specified by the manufacturer. During the static test, it involves lifting the masses for 1 hour and checking for any descent. The descent of the load must not exceed **100mm during 10 min**. After the one-hour static test, it is necessary to check that there is no irreversible deformation.
Gallows Stem (of a bicycle) Gibbet Punt (in rugby)
Hoisting block
Load test before first use and recommissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
   
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Furniture lift

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Furniture lift
Load test before first use and recommissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
During dynamic testing, it involves moving the loads through all possible positions specified by the manufacturer. During static testing, it involves lifting the masses for 1 hour and checking for any descent. The descent must not exceed 100mm during 10 min. After the one-hour static test, it is necessary to check for any irreversible deformation.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Waste skip - Balers and waste compactors

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Garbage truck
Load test before first use and return to service.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 90 days **Dynamic test + 10% of the SWL** Indefinite duration
In dynamic testing, it consists of moving the loads into all possible positions specified by the manufacturer. During the static test, it consists of lifting the masses for 1 hour and checking for any descent. The descent must not exceed 100mm during 10 min. After the one-hour static test, it is necessary to check that there is no irreversible deformation.
Bale press
Waste compactor
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Lifting accessories

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Sling, cable, chain
Load test before first use and recommissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 12 months **Dynamic test + 10% of the SWL** No defined duration
In dynamic testing, it consists of moving the loads into all possible positions specified by the manufacturer. During the static test, it consists of lifting the loads for 1 hour and checking for any descent. The descent must not exceed 100mm over 10 minutes. After the one-hour static test, it should be verified that there is no irreversible deformation.
Clamp, hook, spreader bar, snatch block, magnet, coupler, suction cup
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.

Personal Protective Equipment

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Lanyard, harness, lifeline, anchor point, shock absorption system, connectors, balancer
No charge controlNo charge controlNo charge control
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.

Elevator and freight elevator

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Freight elevator
Load test before first use and return to service.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10% of SWL
No defined duration
The dynamic test consists of bringing the loads into all possible positions foreseen by the manufacturer. The static test will ensure that no deformation or deterioration that could compromise the use of the elevator has occurred.
Elevator
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.

Agricultural machine

Device typeCommissioning and recommissioningPeriodic General Inspection (classic)Method for controlling the load test
Lift arm
Load test before first use and recommissioning.
Static test +25% of SWL
Duration 1 hour
Dynamic test + 10 % of SWL
Undefined duration
Load test every 6 months **Dynamic test + 10% of SWL (Safe Working Load)** No defined duration
In dynamic testing, it involves moving the loads to all possible positions specified by the manufacturer. During the static test, it involves lifting the masses for 1 hour and checking for any descent. The fork descent must not exceed **100mm during 10 min** and the tilt must be less than 5° during 10 min. After the one-hour static test, it is necessary to verify that there is no irreversible deformation.
Any machine moving to another location or site, or provided by a lessor, must undergo re-commissioning before use.
Before applying this table, it is important to check the user manual of your devices to determine that there are no contraindications regarding loaded tests.
**Warning:** A load cell cannot be used for your load tests because it does not allow for control of the allowable decrease. Even with an anchor point, the load cell must not be used for proof and trial tests because it does not allow for a stable load, due to the fact that chains/slings, the fork, or the machine's structure will stretch, and therefore the initially measured force will decrease.